MYSORE,
October 31, 2014
Shifting of Tipu’s armoury soon
The shifting of the 18th century armoury belonging to
Tipu Sultan, which was hindering the progress of track-doubling work
between Bangalore and Mysore, will commence in due course.
The
armoury at the Srirangapatana railway station bisects the alignment of
the second track, which cannot be laid until the monument is shifted.
Sources in the South Western Railway told
The Hindu
that when the tender was floated last year inviting bids to translocate the monument, there were no takers.
The
tenders were floated again in June this year and M/s PSL-Wolfe Pvt.
Ltd., which is a firm registered in New Delhi, was awarded the contract.
Translocation
of the armoury as a single block entails moving it from the floor level
from its existing location to a new site 100 metres away.
This
is done by inserting a suitable supporting system underneath the
monument, lifting it using unified hydraulic jacks and transporting it
on suitably-designed carriers.
Besides, the project
also envisages placing the heritage structure at the new location in the
same orientation as at present and integrating the structure with the
new foundation.
Project cost
In
the process, no damage should be caused to the historic structure which
was used to store arms and ammunitions. Sources said this will be the
first time that a monument would be translocated as a single block,
though many structures have been dismantled and reassembled again.
The
project will cost about Rs. 13.66 crore and has to be completed in 9
months from the date of commencement and during this period, the
Pandavapura-Srirangapatana-Naganahalli section will operate as a
single-line section.
Once the monument is shifted, the 13-km single-line stretch on this section will be converted into a double-line section.
The
Bangalore-Mysore double line work is officially slated to be completed
by March 2015, but for the Naganahalli-Pandavpura section till the
monument was shifted.
Shifting of the armoury was a
major roadblock impeding the pace of the track-doubling work ever since
it was noticed in early 2008, and initially there was resistance from
the State Archaeological Survey.
However, a Cabinet
decision was taken to shift the monument but this had to be cleared by
the National Monument Authority of the Archaeological Survey of India
which gave its clearance in early 2013.
Archaeological
experts had pointed out then that the structure was made of lime mortar
and bricks and hence could not be dismantled as in case of structures
built using granite or slab stones.
There was
considerable delay when the ASI had urged the Railways to realign the
track but it was dismissed as impractical as the supporting piers — on
which two major bridges across the river Cauvery on either side of
Srirangapatana railway station was to be laid — had already been
completed.
0 comments:
Post a Comment