Guwahati, March 10: A parliamentary
panel has asked the ministry of railways to make all-out efforts to
clear hurdles coming in the way of its projects in the Northeast so that
early rail linkages can be provided to people of the region.
This was stated in the report of the
department-related parliamentary standing committee on home affairs
tabled in Parliament this month.
“The ministry of railways should analyse
the situation and make all-out efforts to clear the hurdles and should
not leave any stone unturned for ensuring timely completion of the
projects so that early rail linkages are provided to people of the
region,” the report stated.
Railway sources said regular coordination
meetings were being held with state governments to expedite land
acquisition and forest clearance for the projects. The railways are also
in constant touch with the governments and ministry of home affairs to
ensure security at the work sites.
Citing figures on the slow progress of
projects, the report said the Jiribam-Tupul-Imphal linkage venture had
achieved only 20.73 per cent of the physical target while the Bogibeel
rail-cum-road bridge over the Brahmaputra, that is supposed to link the
north and south banks, still has 24.61 per cent work left to be done.
On the Bogibeel project, the railways said
the contract for the superstructure had been recently awarded and
agency was mobilising resources.
The report said work on the Bogibeel
bridge was often disrupted by rebel activities in the area along with
extortion demands by militants and criminals. Moreover, disturbances at
work sites and security threats to railways officials and employees of
contractors also hampered its progress. The project completion target is
December 2015.
While the new railway line between Dimapur
and Zubza (Kohima) is at the geographical survey stage, work on the
Tetlia-Byrnihat and Bhairabhi-Sairang lines is also progressing at a
slow pace. “Only 34.49 per cent of the physical target has been achieved
on the Agartala-Sabroom line and other railway projects, too, do not
give an encouraging picture,” the report added.
The Jiribam-Tupul-Imphal railway line, on
the other hand, has hit a green hurdle, with the forest advisory
committee asking the Manipur government not to start work on the broad
gauge project unless forest clearance is issued.
The railways had earlier started work on
the project in violation of the Forest Conservation Act since 2010. Work
on 15 tunnels had already been started.
The railways informed the committee that efforts were being made to complete the projects within the target dates.
|
0 comments:
Post a Comment